How long does a project take is one of the most common queries for anyone embarking on a building project. Here’s what to expect, honestly.
Stage 1: Brief, Survey & Feasibility
Allow 2 to 4 weeks subject to the scale of the project.
Every project begins with a brief. We spend time understanding not just what you want to build, but why, what the project needs to achieve, how you live, and what the site allows. From there, a measured survey of the existing property or plot is carried out, and an initial feasibility assessment is prepared.
This stage is often underestimated in its importance. Getting the brief right at the start avoids costly changes of direction later.
Stage 2: Concept Design
Consider 3 to 6 weeks.
This is where the design takes shape. Working from the brief and the survey, we develop an initial concept, exploring how the spaces could work, how the building sits on the site, and how the design responds to its context.
Sketch designs are developed, tested, and refined through dialogue with you.
It is important at this stage that we consider the space in 2D and the form in 3D to help us produce a considered design, but also presentation material for our clients.
Stage 3: Pre-Application & Planning
We would propose 8 to 16 weeks, sometimes longer.
This is where most projects encounter their longest wait, and it’s largely outside anyone’s direct control.
A standard planning application takes a minimum of 8 weeks to determine, though in practice 12 to 16 weeks is more common, and complex or contested applications can take considerably longer. When required, Pre-application advice, typically adds 4 to 6 weeks before submission but can significantly improve the quality and predictability of the outcome.
Listed Building Consent applications run alongside planning and add further complexity. Rural and agricultural projects can sometimes involve additional consultation with bodies such as Natural England or the Highway Authority, which extends timescales further.
Stage 4: Technical Design & Building Regulations
To allow for calculations, allow 4 to 8 weeks.
Once planning is secured, the design is developed to a technical level, structural calculations, building regulations drawings, specifications and schedules.
This stage is detailed and thorough; cutting corners here is where projects run into difficulty on site.
Building Regulations approval, either through a Full Plans application or a Building Notice, is required before work begins.
Stage 5: Tender & Contractor Appointment
To allow for sufficient time and due diligence, allow 4 to 6 weeks.
Drawings and specifications are issued to contractors for pricing.
Quotes are reviewed, clarified, and compared.
A contractor is appointed and a programme agreed.
Stage 6: Construction
Highly variable, typically 3 to 18 months depending on scale and complexity of site works.
A single-storey extension might take 12 to 16 weeks on site. A full barn conversion or new build could run to 12 to 18 months.
The programme depends on the scale of the project, the contractor’s resource, and the inevitable discoveries that come with any building work.
So, What’s the Total?
A straightforward extension with no complications: 9 to 12 months from brief to completion is a realistic expectation. For a new build or conversion, 18 to 30 months is more typical. For complex projects involving listed buildings, sensitive sites, or appeals: longer still.
The best thing you can do is start early, engage a designer you trust from the outset, and build contingency into your timeline. Projects rarely run ahead of schedule, but good preparation and clear communication mean they don’t need to fall far behind it either.